The Navy Years

Bring In the Portakabins!

Seven weeks, eleven buildings and three nervous school directors

Rota, Spain · 199111 min read
Illustration for Bring In the Portakabins!
Seven weeks to go, and the school directors want trailers. Illustration.

One of the biggest projects we had at Rota was the renovation of the base school. We had the task of renovating the entire school, which consisted of eleven separate buildings.

Each building had three classrooms on each end with a bathroom in the middle, plus a central utility room for the air conditioning and pumps. We were going to demolish everything back to the bare concrete and install all new wiring, plumbing, air conditioning, ceilings, windows and doors.

The contract was awarded in January 1990, with the actual renovation scheduled to take place during the summer of 1991. The key to completing a project like this in such a short period was going to be having all of the materials and appliances on site before we started. Once construction began, I wanted the only thing we had to schedule to be manpower. I did not want to hear that we couldn’t do something because a piece of equipment hadn’t arrived or a shipment of materials was delayed.

There was only one school on the base, and the children had to be back in school by late August, so there wasn’t much room for delays. I also didn’t want the contractor storing all of the materials somewhere off base and then having to haul them to the school as they were needed. So I made the construction of a large warehouse near the school part of the contract. The people in base housing were actually excited about that because they needed a warehouse, and once we finished the school, the base would have the warehouse to use.

Once the warehouse was built, we started filling it. Some of the tile was purchased locally, but a lot of the equipment and materials came from the United States. We even had to bring toilet roll holders over from the United States. That might sound ridiculous, but there was a reason for it. The Navy bought its toilet paper in bulk from the United States, and American toilet paper was wider than the rolls used in Spain. The Spanish toilet paper holders wouldn’t hold the American rolls properly, so we had to use the American holders.

Rota had a port that was used by the Navy to bring in all kinds of supplies, including food for the commissary, clothes for the Navy Exchange and other supplies needed to operate the base. We used that port to receive much of the equipment for the school.

Some of the equipment was pretty interesting. We had little toddler toilets, with the seats only about five inches off the floor, and little sinks that were only about twelve inches off the floor. Once everything was installed, it was the cutest bathroom I had ever seen.

From August 1990 through April 1991, we spent months receiving all of the inventory and carefully organizing it in the warehouse. Everything was put on pallets, with the things that would be used last toward the back and the things we would need first toward the front. We left large aisles throughout the warehouse so that a forklift could get to everything. When construction started, we could simply bring the pallets from the warehouse to the school as they were needed.

We also began using portions of the school itself as a marshalling area. Beginning in April, we fenced off an area at the school and started delivering tile and roofing materials there, even before the school year was over.

We were very careful about keeping track of everything. In February, the contractor did a complete inventory. A week later, two of my inspectors did another complete inventory. A week after that, one of my inspectors, the contractor’s project manager and the superintendent did another complete inventory. Each inventory started in a different place so we weren’t simply following the same sequence and making the same mistake three times.

By then we knew exactly what we had. We had ordered ten percent extra tile, ten percent extra toilets and enough of the other materials to cover what we expected to need. We knew exactly how many light fixtures and light bulbs we had, how many toilets, how many windows and all of the other materials.

The windows were a big item. There were 464 large windows, each about four feet wide and seven feet tall. The classroom walls were essentially walls of windows, and all eleven buildings had these huge windows. We had about twenty extra windows, which was intentional. The idea was that after the project was finished, the maintenance people would have enough spare materials to repair or replace things in the school for years without having to wait for another shipment.

On May 24, 1991, the contractors hit the floor running. The first thing that happened was the removal of the old stuff. The asbestos insulation was ripped off all of the pipes. The old roofs were torn off. The bathroom fixtures were demolished and hauled off base to Spanish landfills. The whole place became a construction zone almost overnight.

There was a buzz of activity around the base because everybody knew the school was being renovated, and the local base news and even a television program picked up on what was going on.

We were fortunate that Rota had a very unusual weather pattern. It seemed to me that it only rained once a year, during the first two weeks of October, and the rest of the year it practically never rained. The old saying, “The rain in Spain falls mainly on the plain,” seemed pretty appropriate for that part of Spain. Rota was on the Atlantic coast, while inland toward Seville and Morón the country opened up into the broad, dry Andalusian plain. Morón was noticeably hotter and drier than Rota.

That worked in our favor because we could have the roofs opened up during the summer with very little concern about rain. By the end of the first week, the old stuff was gone. We had bare concrete foundations, the old linoleum was gone, the walls were bare, the old lights had been removed and disposed of, and we were ready to start putting the new school back together.

The contractor had organized the work into teams. Independent window installers were working on the new windows, and an independent roofing crew was working on the new roofs. Ten of the eleven bathrooms were demolished, but we kept one operational for the construction crews. Once some of the new bathrooms were finished, we would renovate the last one. At the same time, the electrical crews were installing all new wiring, the plumbers were installing new plumbing, and the air-conditioning crews were installing new compressors, air handlers and ductwork. The electrical, plumbing and air-conditioning crews were all coordinated by the contractor’s foremen and general foremen.

It was like a finely tuned orchestra. Everybody had a job, everybody knew what his job was, and the different crews were working around each other without getting in each other’s way. We were rocking. And a big part of the reason we were rocking was that the materials were already there. If somebody needed something, we didn’t have to wait for a truck to come from somewhere or wonder when a shipment would arrive. We could go to the warehouse, get what we needed and keep moving.

I would stop by the school in the mornings to see how things were going. We also had a weekly project review with the contractor’s project manager, my inspector and the contractor’s superintendent. Those meetings usually lasted about an hour. My inspector was at the project full time and knew exactly what was going on, so the meetings were mostly about progress and any problems that needed to be addressed. There weren’t many problems. We had planned this project to the T.

On Tuesday, July 2, right in the middle of all this ongoing construction, I was summoned to the conference room in the school administration office. The office was in a separate building away from the school grounds where we were doing the renovation. I walked into the room thinking the school people wanted to make some changes to the project or had some question about something we were doing.

The principal knew me and introduced me to the man who was in charge of all the Department of Defense Dependents Schools activities in Spain. DODDS was outside of the Navy chain of command, so this was a different organization from the one I normally dealt with. Then he introduced me to another man who was the big cheese, the Director of DODDS for all of Europe. He had flown in from London for the meeting.

The guy from Madrid looked at me and said, “What are we going to do?”

I looked at him, probably with a little more confusion than I actually felt, and said, “Do about what?”

“You know, the building of the school.”

I said, “I just came from there and we are doing well. What are you all concerned about?”

They said, “Come on Dennis, today is July 2 and we have to have the school ready for the children by August 19, and that is only about seven weeks from now. There is no way you will finish, so we want to talk about bringing in some portakabins so the children will be able to go to school at the end of the summer.”

I said, “So you guys want to bring in portakabins, essentially trailers, to set up on the school grounds?”

They all said yes. The man from London explained that there were some portakabins available at Morón that had been used as temporary classrooms for Air Force personnel at Morón Air Base. They could be trucked to Rota fairly easily, but they would need power and all of the other things necessary to make them usable as classrooms.

I sat back and listened to them and thought, these guys are smart, but none of them knew squat about construction. I said, “Guys, guys, the project is going well. I do not think we need to worry about finishing on time.”

The three of them looked at me as if I had suddenly grown a second head. “How can you say that? There are hundreds and hundreds of windows to install, all the bathrooms have been demolished, and there are eleven roofs to install. We just don’t see it happening in less than seven weeks from now.”

I turned to the man from London. “Excuse me sir, you are in charge of all DODDS for Europe?”

He said yes. I said, “To get to that position I imagine you have been in education and education administration for a lot of years.”

He said yes, over thirty years. I said, “Well, while you guys have been doing that, I have been managing many hundreds of construction projects and I am actually pretty good at what I do.”

Then I explained why I understood their concern, but why they didn’t have all of the information I had. “You do not know how long it takes for a four-man crew to install the tile in the bathrooms. You do not know how long it will take to install one or ten of the windows, and more importantly, you do not know how many people we have working there.”

“Sir, the real key to meeting a construction deadline—the single most important thing—is eliminating delays caused by materials and equipment not being on site when they’re needed. We ordered all the materials, fixtures, and mechanical equipment last year in preparation for this job. Everything is already here, either on the school grounds or in the warehouse just outside the school property. I had everything inventoried, checked, and rechecked every way I could think of, multiple times. We know what we have, where it is, and that it’s ready when the crews need it. We’ve already eliminated the single biggest risk of missing your school deadline.”

I realized I had not come prepared to explain all of those details to them, so I suggested that we meet again on July 10, a little over a week later, and I would go over the details with them. “In the meantime, don’t push the button just yet on getting the portakabins, okay?” The big boss agreed. He would fly back down from London by July 10, and we agreed to meet at 10:00 that morning.

I said, “But not here. I will get a table and a meeting room prepared at the school and will meet you there at ten a.m., okay?” They agreed, and the meeting was adjourned.

When July 10 came around, I met their car at the entrance to the school and brought them to one of the classrooms that the contractor had cleared for our meeting. He had set up a table and chairs and had even provided a coffee pot and several pitchers of water. As we settled in, there was a hub of activity all around us. There were probably fifty or sixty men working throughout the school. Men were carrying materials, installing windows, working on the roofs, running electrical wiring, installing plumbing and doing all the other things that had to be done. The whole place was busy, like a hive of bees.

I had come prepared this time, and I took out my notes. I said, “As of today, of the eleven bathrooms, two are complete with the new tile and fixtures mounted. Four have all the tile in place, and of those four, two are almost finished with the installation of the fixtures. Of the eleven roofs, three are complete and two more will be complete by Friday. Of the 464 windows, we have installed 204 to date. Of the eleven classroom buildings, nine have all the ductwork installed, and all but one have all of the air compressors installed. What is left are the air handlers and final hookups and testing once the air handlers are done.”

I referred to my notes. “We expect to do all the testing of the air-conditioning systems by the first week in August, which gives us plenty of time to adjust and balance the flows.” As we were sitting there, coincidentally, a four-man team arrived at the building across from where we were sitting. They went to a stack of ten windows that were leaning against the wall and began pulling them out one at a time to install them.

I pointed toward them. “See that four-man team installing the windows there? There are three teams doing that throughout the job site.” I sat back and said, “I hope these numbers show you that this job is going well, but I am prepared to do this every week with you all. How about we meet next Wednesday and let’s see where we are?” They thanked me for the information and agreed to meet the following week.

And we did. At that meeting, the DODDS guy from London looked at me and said, “I am sorry we did not trust your judgment. It is apparent to me that you will finish on time, so I personally do not need to meet here anymore. But would you please meet weekly with these two guys so they can report the progress back to me?”

I said, “Sure.”

And that was pretty much the end of the matter. We finished the school a few days early, and the kids moved into their renovated, good-as-new school with no delays.