How It's Done
Hooking Up a Giant in the North Sea
What It Was Really Like to Live and Work Offshore

Most people look at a picture of a big offshore oil platform and figure that once you've got that enormous hunk of steel standing out in the ocean, the hard part is over. Well, I've got news for you. You're not even close to being finished. You've got the structure in place, you've got all these great big modules sitting on top of it, and you've got millions of dollars' worth of machinery, piping, electrical equipment and instrumentation scattered all over the damn thing. But none of it works yet. Nothing is connected, nothing has been tested, and you couldn't produce a barrel of oil if your life depended on it. Now comes the fun part. It's called hook-up and commissioning, and believe me, there's a hell of a lot more to it than the name suggests.
Hook-up is pretty much what it sounds like. You connect everything together. Pipes have to be welded, electrical cables pulled and terminated, instruments installed, equipment lined up, and a thousand other things finished before the machinery can do what it's supposed to do. Then comes commissioning, which is where you find out whether all that stuff actually works. You test the individual pieces, then you test the systems, and eventually you've got to make the whole damn platform work together. I got a pretty good education in all of that on Chevron's Ninian South platform in the North Sea.
I'd been working for John Mackin in London, doing schedules and estimates, when he landed the Chevron contracts for Ninian South and Ninian Central. John put together the teams and made me Construction Supervisor on Ninian South. I'd worked offshore before, including on Piper Alpha, but this was something altogether different. At the peak of hook-up and commissioning, we had about 1,300 people out there. Roughly 850 were construction craftsmen, another 150 were engineers, planners, schedulers, supervisors and managers, and the rest were supporting the operation. And we weren't working an eight-hour day and going home. We were running twenty-four hours a day, seven days a week, in the middle of the North Sea.
Now picture what you've got going on with that many people. Welders are welding, pipefitters are running pipe, electricians are pulling cable, instrument technicians are doing their thing, riggers are moving equipment, and engineers are trying to solve problems that nobody discovered until somebody actually tried to build what was on the drawing. All of them are working in the same enormous structure, and half the time one fellow can't do his job until somebody else finishes something first. The pipefitters need some steel installed before they can hang a pipe. The electricians need a cable tray. The instrument people are waiting for the pipefitters. Two different crews need the same crane. That's just the nature of construction, except you're doing it miles offshore, and you can't exactly run down to the hardware store when somebody forgets a valve.
One of the first questions you might ask is where in the hell do you put 1,300 people out in the ocean? Well, we had two enormous accommodation barges sitting alongside the platform. They called them flotels, which is just a fancy name for floating hotels. One housed more than 500 men, and the other held about 500. Later, when we finished commissioning the platform's own living quarters, we could put another 140 men aboard Ninian South itself. Those flotels were semi-submersibles, which meant they had big pontoons submerged below the surface of the water with columns supporting the accommodation decks above. Under normal conditions they were remarkably stable, much more so than an ordinary ship, and that's important when you've got hundreds of men trying to sleep between shifts.
Living on one of those things was an experience all its own. You had sleeping quarters, a galley, dining rooms and the permanent crew that operated the vessel. Everybody ate together, although people naturally found their own favorite tables. There wasn't any going home after work, no stopping off for a beer with the boys, and no jumping in your car to go somewhere. You were out there until it was time for your helicopter ride home. When your shift was finished, you ate, cleaned up, got some sleep and did it all over again. Meanwhile, the other shift was out on the platform keeping the work going. The flotels made that whole operation possible. Without them, there was no way we could have put enough craftsmen offshore to finish the job.
Now, one of the things that made Ninian South so interesting was that you couldn't manage the work the way you might manage an ordinary construction job. On land you can divide up a project by buildings or floors or areas. That doesn't work very well when you've got a pipe that starts in one module, runs through two or three decks, passes through a bunch of structural steel, winds around cable trays, and finally ends up somewhere on the other side of the platform. We decided to organize the work around twenty-three separate systems. Main process, electrical power, life support, communications, controls, drains and all the other things that eventually had to come together to make the platform operate. Every one of those systems had somebody responsible for getting it completed.
Take structural steel, for example. We had a Structural Engineer and a Structural General Foreman. The engineer understood the design and the drawings, and the foreman controlled the men who actually did the work. Between them they were responsible for stairs, handrails, antenna towers, lifeboat davits, boat fenders and every other piece of miscellaneous steel scattered around that enormous platform. And you couldn't just tell those two fellows to go build it and expect miracles. They needed welders, riggers, helpers, steel, welding rods, equipment, scaffolding, drawings and answers from engineering. They needed crane time, too, and they had to coordinate with all the other crews working around them.
The drains were another good example. We had miles of drain piping running all over that platform. The engineer and General Foreman responsible for drains had to know that entire system, no matter where the piping went. They needed pipefitters and welders, valves, fittings, supports and everything else necessary to get the job done. And if they needed structural steel installed before they could hang their pipe, they had to get the structural people involved. That sort of thing happened constantly. Twenty-three systems, all trying to move forward, and every one of them depending on somebody else for something.
So how in the hell do you keep track of all that? Well, I came up with a system that worked pretty damn well. Every Friday night we had a big meeting. I sat at the head of the table with the General Superintendent, the head of Design, the Materials Manager and a couple of planners. Directly in front of me were two chairs. I called them the hot seats. One system at a time, the engineer and General Foreman responsible for that system came in and sat down together. Then we went through their work. What did you accomplish this week? What were you supposed to accomplish that you didn't? Why didn't you get it done? What are you going to do next week, and what do you need to get there?
Now here's what made those meetings useful. If the drains people said they couldn't get the work done because they didn't have enough pipefitters, the General Superintendent was sitting right beside them. He could explain where the men were and whether he could move some over. If they needed an engineering drawing, the head of Design was right there. If a valve was missing, the Materials Manager had to tell us where it was and when we'd get it. And if somebody needed a crane that another crew was using, we could work that out too. We weren't just sitting around listening to excuses. We had the people who could solve the problems right there in the room.
When we finished with drains, those two fellows got up and the next pair came in. Maybe structural, maybe electrical, maybe another piping system. Same questions, different people. We went through all twenty-three systems that way, and the planners recorded what everybody had agreed to do. By the time we finished, I knew which systems were moving, which ones were falling behind, what was holding them up and who was supposed to fix it. I didn't need to know where every valve was or every weld that had been made. That's what the engineers and foremen were supposed to know. I needed to know whether the whole operation was moving toward completion.
There was another complication that people who've never worked offshore might not think about. Our management people worked rotating schedules, generally two weeks offshore and two weeks home. We called the two people sharing the same position back-to-backs. One fellow would work his two weeks, get on a helicopter and head home, and the other fellow would come out and take over. But here's the problem. You couldn't have somebody arrive on Monday and spend three days figuring out what his partner had been doing. The work didn't stop just because somebody changed crews.
I made it clear that the two men sharing a position were, as far as I was concerned, one person. They had one job, one responsibility, and they were both accountable for it. They kept a common diary where they recorded engineering decisions, material shortages, field changes, problems and anything else the next fellow needed to know. We also staggered the rotations so the engineer and the General Foreman for a particular system didn't both go home at the same time. One of them had already been aboard for a week when the other changed out. That way we always had somebody familiar with the current work.
Every so often I'd have the engineers bring their diaries to the Friday meeting, and I'd pick one up and flip through it. I wanted to make sure they were actually recording things as they happened, not trying to remember two weeks' worth of decisions the night before their back-to-back arrived. By Friday everybody had been aboard for several days, the turnovers were finished, and they were supposed to know what was going on. There wasn't any such thing as saying, "Well, I just got here." As far as I was concerned, their position had been there the whole time.
Of course, with that many people working offshore, we also had to worry about keeping them alive. One of the biggest concerns was somebody falling into the North Sea. That water was cold enough that a man didn't have much time before hypothermia began taking away his ability to control his muscles. Everybody wore insulated International Orange coveralls, which gave a fellow a little protection if he went into the water, but not very much. We figured we had only a few minutes to get somebody out before he was in serious trouble.
Chevron hired two standby boats for that very reason, and these were interesting boats. They had originally been Scottish fishing vessels, and the owners had converted the fish holds by installing long benches so each boat could carry as many as 800 people in an emergency. They were contracted to stay on station for thirty days at a time. And here's the part that amazes people when I tell them about it. Those boats never stopped running their engines. Not at night, not during meals, not when the crew was sleeping. Twenty-four hours a day, seven days a week, those engines were running.
They couldn't tie up to the platform, and they couldn't anchor, so they stayed about fifty to one hundred feet off the downwind, down-current corner. As the wind and current changed, they changed position. They'd motor along at idle speed, using just enough power to hold themselves in place. The whole idea was that if somebody went over the side, one of those boats could be moving toward him immediately. They carried nets, safety rings and rescue equipment, and the crews were trained to get a man out of the water and onto the deck within two minutes. Two minutes! Think about that. Those fellows sat out there day and night, month after month, ready to jump into action if somebody needed them. Most of the construction workers probably never gave those boats much thought, but I certainly did.
Another thing about a project that size is that you can't run it entirely from an office. Roger Loper was the manager of the whole Ninian Field development, and he used to come offshore about every three weeks. He'd arrive by helicopter, and we'd spend an hour or so going through the schedules for all twenty-three systems. The planners would show him which systems were ahead, which ones were behind and what we were doing about the problems. Roger could look at those schedules and get a pretty good idea of where the job stood, but he didn't stop there.
After the meeting, Roger, my General Superintendent, the head of the systems design group and I would put on our hard hats and walk the platform. And when I say walk the platform, I mean we walked the damn platform. We'd start at the top and work our way down through every module and every level. Roger wanted to see the actual work. He'd been looking at lines on schedules for an hour, and now he wanted to see whether those lines represented real progress. That's a lesson I never forgot. A schedule can tell you what somebody says is happening. Walking the job tells you whether you should believe him.
I took that business of knowing the platform pretty seriously myself. In fact, I walked every walkway and stood on every square foot of Ninian South. I'm not kidding. I even went down inside one of the enormous steel legs to inspect piping we'd completed. Inside that leg were huge tanks for drilling water and diesel fuel. The platform had something like 20,000 barrels of diesel-storage capacity, about 840,000 gallons. Before we started producing oil, the big generators ran on diesel. Once production began, they could burn the natural gas coming from the wells.
Anyway, I climbed down inside that leg using these caged ladders. As I remember it, one ladder took me down to the top of the drilling-water tank, and another offset ladder continued farther down toward the diesel tank. The tanks were empty at the time, so I could get down there and inspect the piping. Going down wasn't too bad. Coming back up was a whole different story. Altogether, it was something like four hundred feet of ladder, and I was a big fellow. I must have stopped five times on the way back up, leaning against that tight circular ladder cage and catching my breath. I can tell you one thing. When I finally got back to the top, I knew I'd done some climbing.
But that's the kind of thing I believed in. If you're responsible for building something, you ought to know what you're building. Not just what the drawings show, and not just what the schedules say. You ought to get out there, walk around, talk to the people doing the work and see it with your own eyes. That's how you find out what's really going on.
Now, all of this work had one purpose. We weren't out there just to install pipe, pull cable, put up handrails or hold meetings. We were there to get that platform ready to produce oil. And that's what makes hook-up and commissioning such an interesting part of offshore construction. You can have a beautiful platform with millions of dollars' worth of machinery installed, but until the systems work, you've got nothing but an expensive piece of real estate sitting in the ocean. The generators have to run, the piping has to be connected, the instruments have to work, the controls have to function, the process equipment has to operate, and all the other systems have to come together.
We broke Ninian South into twenty-three systems because that's how we could control the construction and commissioning. But when it came time to produce oil, those twenty-three systems had to operate as one enormous machine. That's the real trick. You take thousands of individual pieces, built and installed by hundreds of different people, and turn the whole thing into one functioning offshore oil platform.
When I look back on Ninian South, I don't just remember the steel and machinery. I remember the people who made it happen. The welders, pipefitters, electricians, riggers, engineers, planners, foremen, barge crews, standby-boat operators and everybody else who had a hand in the job. We had about 1,300 people working out there at the peak, and every one of them had something to contribute. Somehow we had to get all those people, all that equipment and all those systems working toward the same objective.
And there I was, a Coco Solo boy from the Panama Canal Zone, sitting in the middle of it all, trying to keep twenty-three systems moving and a thousand-plus people working while we turned an enormous pile of steel and machinery into an operating oil platform.
It was a hell of a job. But I'll tell you something. I wouldn't trade that experience for anything.