How It's Done
How Do You Put a 300-Foot Steel Jacket on the Ocean Floor?
Seven pictures, start to finish
Well, you don't just pick the damn thing up and drop it in the water. There's quite a bit more to it than that.
A Note About the Illustrations
I created these illustrations using artificial intelligence as my paintbrush. The engineering knowledge, construction sequence, and technical direction came from my own experience working offshore. AI simply helped me turn that knowledge into pictures.
To keep things simple, I've illustrated a jacket with four legs containing foundation piles. Larger offshore jackets may have eight, twelve, or even more pile locations.
These are illustrations, not actual photographs of a particular offshore installation. They're intended to show how we put these enormous steel structures on the ocean floor.
Picture 1 — The Tow-Out

These enormous steel structures are usually built lying on their sides.
Once fabrication is complete, the jacket is slid onto a transportation barge. Depending on the fabrication yard, this may involve hydraulic jacks, cables, winches, or a combination of methods. Moving thousands of tons of steel from solid ground onto a floating barge is quite an operation in itself.
Picture 1 shows a tugboat towing the barge and its enormous cargo toward the offshore location where the jacket will eventually stand. For particularly large jackets, it may take two or three powerful ocean-going tugboats to get the whole damn thing out there.
And these aren't always short trips. Jackets fabricated in shipyards in Spain or the Netherlands may have to be towed hundreds or even thousands of miles to oil fields off Scotland or Norway. One particularly impressive example was the North Rankin A jacket off the coast of Western Australia. That enormous structure was fabricated in Japan and towed approximately 6,000 kilometers to Australia.
Just imagine towing thousands of tons of steel across that much open ocean, with storms, waves, and everything else Mother Nature might throw at you. The marine insurance alone on some of these operations can be enormously expensive. And you certainly don't want to lose the damn thing halfway across the ocean.
Picture 2 — The Launch

Picture 2 shows the jacket being slid off the barge and into the water. This can be done several ways, depending on the size of the jacket and the equipment available. It may involve cables, hydraulic jacks, winches, and sometimes another tug helping control the movement.
As you can see, once the jacket starts sliding, the big end goes first. The structure begins to tip as it leaves the barge and slides into the water. To somebody seeing it for the first time, it can look pretty wild, but this is a carefully planned operation.
Picture 3 — The Jacket Floats

Now you might be wondering how thousands of tons of steel can possibly float. The answer is pretty simple. The large steel tubes that make up the jacket are sealed watertight and filled with air. That trapped air provides enough buoyancy to keep the whole damn thing afloat, even though most of the structure is below the surface.
Once the jacket is floating safely, two or three men climb aboard and make their way to a control panel. Their job is to carefully control the flooding of selected legs and compartments.
By allowing seawater to enter in a controlled sequence, they gradually change the balance and buoyancy of the structure, causing it to rotate from a horizontal position toward vertical.
Think about what they're doing. They're deliberately letting water into a floating steel structure weighing thousands of tons, and controlling exactly how it tips over. Too much water in the wrong place or at the wrong time could create one hell of a problem.
Picture 4 — The Transition to Vertical

Picture 4 shows the jacket in the middle of its transition from horizontal to vertical. The controlled flooding has started, and the structure is slowly rotating upward in the water.
The crew operates the flooding controls and monitors how the jacket responds. This isn't something you rush. Everything has to be done slowly and carefully so the jacket comes upright without getting away from you.
Remember, this is all happening offshore with thousands of tons of steel floating in the ocean.
Picture 5 — Moving the Jacket into Position

Picture 5 shows the jacket floating vertically, with its bottom probably 20 to 30 feet above the ocean floor. We're working in approximately 300 feet of water, so most of this enormous structure is now underwater.
I've shown three powerful tugboats maneuvering the jacket toward its final location. Two are pulling while the third helps control its movement.
And here's something important. Nobody is guessing where to put this thing. The oil field has already been explored, the oil reserves have been proven, and the engineers have determined exactly where the jacket needs to stand.
The location has been surveyed, and the tugboats carefully maneuver the jacket into position over that predetermined spot.
Picture 6 — Setting the Jacket on the Ocean Floor

Picture 6 shows the three men climbing off the jacket and onto a tugboat. Their work is finished. The compartments used to control its buoyancy have been flooded as required, and the enormous steel structure is now sitting on the ocean floor, exactly where it was supposed to go.
At this point, the jacket's tremendous weight provides temporary stability, but we're not finished yet.
Remember, this thing has to stand up to ocean currents, high winds, enormous waves, and some pretty nasty storms. We certainly don't want thousands of tons of steel deciding to take a little trip across the ocean floor.
That's where the piling comes in.
Picture 7 — Driving the Piling

Picture 7 shows a large derrick barge anchored alongside the jacket. Its enormous crane is positioning a steam hammer on top of a steel pipe pile that has been lowered through one of the jacket's corner legs.
The pile follows the same angle as the jacket leg, which in this illustration has what we call a 1-in-12 batter. In other words, the leg slopes outward one foot for every twelve feet of vertical height.
The hammer drives the pile down through the jacket leg and deep into the seabed. This operation is repeated for each of the four legs. The piles are then securely connected to the jacket, anchoring the entire structure to the ocean floor.
Now we have an enormous steel jacket standing in 300 feet of water, securely fastened to the seabed and ready for the next stage of construction.
But We Still Don't Have an Oil Platform!
All we've done is install the foundation.
We still have to bring out the enormous topside modules containing the drilling equipment, processing facilities, generators, control rooms, living quarters, and everything else needed to operate an offshore oil platform.
And getting those modules lifted hundreds of feet into the air and set onto the jacket is another pretty interesting operation.
But that's another story.