How It's Done
Installing the Deck and Modules
Turning a jacket into a platform
In our previous post, we showed how an offshore jacket is transported to its location, launched, positioned upright, and secured to the seabed. Now we're going to install the deck and modules that will eventually turn that steel structure into a working offshore platform.
Phase One — Preparing for the Deck Installation
The jacket has now been installed, and the piles have been driven more than 100 feet into the seabed. The piles are secured to the jacket by filling the space between the outside of the piles and the inside of the jacket legs with cement. This space is called the annulus. Once the cement has hardened, the jacket is firmly connected to the piles and anchored to the seabed. The tops of the four piles have been trimmed to the proper elevation and beveled in preparation for receiving the deck. The four legs of the deck structure will be carefully lowered, or stabbed, into the tops of the four piles. Once properly positioned, the connections will be welded to permanently secure the deck to the jacket and piling system.
A note about the illustrations: We have painted the deck legs red so readers can clearly distinguish them from the jacket. In actual offshore construction, the principal structural components are generally painted yellow. There is an important reason for that color identification. The yellow members designate the main structural components, which are not to be casually cut or welded onto as construction proceeds. They are essential to the structural integrity of the platform.
Picture One — Lifting and Positioning the Deck

Like the previous post, these are illustrations I made with AI as my paintbrush, not photographs.
The derrick barge has lifted the prefabricated deck structure off a cargo barge and is now positioning it directly over the jacket. The four deck legs, shown in red for clarity, must line up with the four piles extending above the jacket. The crane operator will carefully lower the deck, allowing each leg to stab into its corresponding pile. This is a precision operation involving a very heavy load suspended from a floating crane. The crane operator, rigging crew, and personnel on the jacket must work together to ensure that all four legs are properly aligned as the deck is lowered into position.
Picture Two — Deck Installed

The deck is now in place, and the structural connections between the deck legs and the piles have been welded. A set of stairs has also been installed to provide access from the main deck down to the jacket's lower level. Notice that the stairs, walkways, and grating are made of galvanized steel. Galvanizing is a process in which fabricated steel is dipped into a bath of molten zinc, coating the steel with a protective layer that gives it its distinctive shiny gray appearance. The zinc coating provides excellent corrosion protection, particularly important in the harsh saltwater environment of an offshore platform.
Picture Three — Installing the First Module

The derrick barge has lifted the first prefabricated module off a cargo barge and is now lowering it onto the top of the deck. Notice that at this stage, the module is simply sitting on the deck. It has not yet been permanently connected to the deck structure. Those connections will be completed as installation work progresses.
Picture Four — Installing the Living Quarters and Helideck

Picture Four shows the installation of the last module in our example, consisting of the living quarters and the helicopter landing deck, commonly called the helideck. With all these modules now in place, the next major installations would be the drilling modules and the drilling tower. But that work, along with connecting all the equipment and systems, takes place during the Hookup and Commissioning phase.
And that's a different story.